Basin “N” Sewer Rehabilitation Project Underway

Hartselle Utilities is launching a sewer rehabilitation project in our Basin “N” area of service to improve the reliability, safety, and performance of our wastewater system.  Ranger Enviromental construction company will be performing the work, which includes rehabilitating mains, manholes, and select sewer laterals. This essential project will:

  • Replace and repair aging sewer pipes to extend the life of the system and improve overall service.

  • Correct structural deficiencies in sewer mains that could lead to sewage overflows. This includes upsizing pipes as needed to accommodate higher flows and prevent future issues.

  • Use a combination of pipe bursting and open cut methods to complete the work effectively.

  • Rehabilitate or replace approximately 1.25 miles of sewer mains.

Lateral rehabilitation will not extend beyond the utility easement. Upon completion of construction, Ranger Environmental will restore all areas impacted by construction activities.

Hartselle Utilities understands the inconvenience projects like this can cause and appreciates our customers’ patience. Ranger fully understands the high expectations HU places on maintaining reliable, respectful service throughout the project.

Project Timeline

  • Expected Construction Start Date for Schedule 1: June 16, 2025

  • Expected Construction Finish Date for Schedule 1: October 14, 2025 (Weather Permitting)

  • Schedule 2 is expected to begin following the completion of Schedule 1 and will be completed by February 11, 2026.

If you have any questions or concerns, please contact us at (256) 773-3340.

A PowerPoint presentation with more detailed information is available for download here.