Electric System Connection Fees

Secondary Services:

Residential overhead secondary service within 150 ft. of primary and 25 kva transformer: $230.00
Additional cost of overhead secondary over 150 ft.: Actual Cost
Transformer over 25 kva: Actual Cost 

Residential underground secondary service within 150 ft. of primary and 25 kVa transformer: $800.00*
Additional cost of underground secondary over 150 ft.: Actual Cost
Transformer over 25 kva: Actual Cost 

Residential development (two or more lots) for underground secondary services- up to a 50 kva transformer: $350.00 per lot*
Transformer over 50 kva: Actual Cost

Primary Services:

Primary overhead extension under 150 ft.: No Cost
Additional cost of extension over 150 ft.: Actual Cost

Primary underground extension under 150 ft.: $5.35 per ft.
Additional cost of extension over 150 ft.: Actual Cost

Additional Fees:

Initial 1 or 3 phase: Actual Cost less standard transformer credit
Additional services: Actual Cost
Service upgrades: Actual Cost less depreciated transformer credit
1 to 3 phase conversion: Actual Cost
Primary extensions: Actual Cost

Reconnection Charges: For services disconnected for non-payment; $40.00 during office hours, and $65.00 after hours.